Decoto Reservoir Seismic Improvements and Roof Replacement Project

Background

The Project will involve the replacement of the reservoir’s existing roof and seismic strengthening of its structural system, together with a new reservoir liner, installation of ventilation and lighting, and new valves.  Construction is scheduled to run from late 2024 to early 2026.


Location

The Project is located in Fremont, CA, between King Avenue and Appian Way.  Access is through Florence Street in Union City. 


CEQA

ACWD approved a Final Initial Study/Mitigated Negative Declaration (IS/MND) for the Project at its July 11, 2024 Board Meeting.  During the 30-day public review period that ended on June 26, 2024, one comment was received.  The comment and response are appended to the Final IS/MND

 ACWD filed a Notice of Determination on July 12, 2024.


Project  Contacts

ACWD Project Manager
Carlos Sempere
Email Carlos Sempere
Phone: (510) 668-4484

 

ACWD Public Affairs
Sharene Gonzales
Email Sharene Gonzales
Phone: (510) 668-4208


Return to Current Projects page